ANALISIS RISIKO BERDASARKAN PERANAN OWNER DAN KONSULTAN PADA PEKERJAAN JALAN KABUPATEN KERINCI

Authors

  • Dezi Purmana
  • Bahrul Anif
  • Yusrizal Bakar

Abstract

This study aimed to answer two main problems associated with the risk of delay
completion of the work on road construction projects, including the first explain aspects
of risk that must be considered in the process of execution of the work, especially
coming from the owner and consultant planners, the second describes the priorites of
each aspect of good risk the owner or consultant planner as an initial step for handling
the impact. By using several analytical approaches, such as the approach to risk
breakdown structure and analytical hierarchy process, the results showed that three are
three criteria that should be cosidered a risk to overcome delays in the completion of
such work is legal and contractual risk by 45%, amounting to 29% of construction risk
and economic risk of 27%. While the parties who contributed to the delay when viewed
from the role that each party is 85.7 % delay caused by the consultant and the remaining
14.3 % due to the owner role.
Keywords : Risk Management, Risk Impact

References

Adi Tisna Rayadi (2003), Kajian Aspek Risiko

Keterlambatan pada kelayakan

Proyek, Tesis, Departemen Teknik

Sipil, ITB

Donald S. Barrie (1992), Professional

Construction Mangemen, 1992.

Ervianto, W.I (2002), Manajemen Proyek

Konstruksi, Penerbit ANDI,

Yogyakarta.

Felicitas Sri Marniati (2003), Kajian Risiko

Pada Konstuksi Jalan, Tesis,

Universitas Indonesia, 2003

Farid, M (2005), Identifikasi factor-faktor

penyebab permasalahan

pengembangan Kemampuan

Kontraktor Kecil dan Menengah

dalam Dinamika Otonomi Daerah

(Studi kasus Kabupaten Bandung),

Tesis Magister, Institut Teknologi

Bandung.

Flanagan, R & Norman, G. 1993, Risk

Management and Construction.

Blackwell Science, London.

Hendricson, (2000), project Management for

contruction.

Kangari, R. 1995. Risk Management

Perceptions and Trends of U.S.

Constuction.

Journal of Counstruction Engineering

and Management. ASCE.

Oberlender, (2000). Project Management

for Engineering contruction.

Pribadi K.S, Affandi.F, Firmadi.A. (1998),

Jurnal Teknik Sipil Vol. 5 No. 1

Januari 1998, Institut Teknologi

Bandung.

Romelda Promiastria Simamora (2008),

Penyebab Terjadi Risiko Kegagalan

Proyek, Tesis, USU Singarimbun,

M. (1989), Metode Penelitian

Suvey, LP3S, Jakarta.

Tika, M.P (2005), Budaya Organisasi dan

Peningkatan Kinerja Perusahaan,

Penerbit Bumi Aksara.

Efrizon (2014), Tinjauan Risiko Pada

Objek Jalan Kabupaten Pasaman

Hingga Perbatasan Sumatera

Utara,

Toruan, R.L. (2005), Panduan Penerapan

Manajemen Mutu ISO 9001:2000,

PT. Elex Media Komputindo,

Jakarta.

Wiryodiningrat, P. (1997), ISO 9000 Untuk

Kontraktor, PT. Gramedia Pustaka

Utama, Jakarta.

Winarno Surakhmad (1985), Pengantar

Peneliti Ilmiah. Cet. II. Bandung:

Taristo

Published

2015-06-20