ANALISIS RISIKO BERDASARKAN PERANAN OWNER DAN KONSULTAN PADA PEKERJAAN JALAN KABUPATEN KERINCI
Abstract
This study aimed to answer two main problems associated with the risk of delaycompletion of the work on road construction projects, including the first explain aspects
of risk that must be considered in the process of execution of the work, especially
coming from the owner and consultant planners, the second describes the priorites of
each aspect of good risk the owner or consultant planner as an initial step for handling
the impact. By using several analytical approaches, such as the approach to risk
breakdown structure and analytical hierarchy process, the results showed that three are
three criteria that should be cosidered a risk to overcome delays in the completion of
such work is legal and contractual risk by 45%, amounting to 29% of construction risk
and economic risk of 27%. While the parties who contributed to the delay when viewed
from the role that each party is 85.7 % delay caused by the consultant and the remaining
14.3 % due to the owner role.
Keywords : Risk Management, Risk Impact
References
Adi Tisna Rayadi (2003), Kajian Aspek Risiko
Keterlambatan pada kelayakan
Proyek, Tesis, Departemen Teknik
Sipil, ITB
Donald S. Barrie (1992), Professional
Construction Mangemen, 1992.
Ervianto, W.I (2002), Manajemen Proyek
Konstruksi, Penerbit ANDI,
Yogyakarta.
Felicitas Sri Marniati (2003), Kajian Risiko
Pada Konstuksi Jalan, Tesis,
Universitas Indonesia, 2003
Farid, M (2005), Identifikasi factor-faktor
penyebab permasalahan
pengembangan Kemampuan
Kontraktor Kecil dan Menengah
dalam Dinamika Otonomi Daerah
(Studi kasus Kabupaten Bandung),
Tesis Magister, Institut Teknologi
Bandung.
Flanagan, R & Norman, G. 1993, Risk
Management and Construction.
Blackwell Science, London.
Hendricson, (2000), project Management for
contruction.
Kangari, R. 1995. Risk Management
Perceptions and Trends of U.S.
Constuction.
Journal of Counstruction Engineering
and Management. ASCE.
Oberlender, (2000). Project Management
for Engineering contruction.
Pribadi K.S, Affandi.F, Firmadi.A. (1998),
Jurnal Teknik Sipil Vol. 5 No. 1
Januari 1998, Institut Teknologi
Bandung.
Romelda Promiastria Simamora (2008),
Penyebab Terjadi Risiko Kegagalan
Proyek, Tesis, USU Singarimbun,
M. (1989), Metode Penelitian
Suvey, LP3S, Jakarta.
Tika, M.P (2005), Budaya Organisasi dan
Peningkatan Kinerja Perusahaan,
Penerbit Bumi Aksara.
Efrizon (2014), Tinjauan Risiko Pada
Objek Jalan Kabupaten Pasaman
Hingga Perbatasan Sumatera
Utara,
Toruan, R.L. (2005), Panduan Penerapan
Manajemen Mutu ISO 9001:2000,
PT. Elex Media Komputindo,
Jakarta.
Wiryodiningrat, P. (1997), ISO 9000 Untuk
Kontraktor, PT. Gramedia Pustaka
Utama, Jakarta.
Winarno Surakhmad (1985), Pengantar
Peneliti Ilmiah. Cet. II. Bandung:
Taristo