PENERAPAN MODEL PENJADWALAN JOB n JOBS m MESIN PARALEL UNTUK MEMINIMASI MEAN FLOW TIME

Authors

  • Lestari Setiawati Laboratorium Sistem Perencanaan dan Pengendalian Produksi Jurusan Teknik Industri - FTI - Universitas Bung Hatta
  • Ayu Bidiawati Laboratorium Perancangan Sistem Kerja dan Ergonomi Jurusan Teknik Industri - FTI - Universitas Bung Hatta

Abstract

This research was implemented  an algorithm of job scheduling models of n jobs m parallels machines for drying process at PT. Torimon. The objective of this research is to minimized mean flow time. The raw material was be made a schedule which is based on customer demand on March (about 842m3). The result of this research find out that mean flow time was equal to processing time of chamber machines.